June 20, 2018 – After some negotiation, our offer for this 80-acre property is accepted.



August 29, 2018 – The Brotherhood, the Sisterhood, family, and friends gather for the first visit all together on the property. We filled it with many prayers that day, and continue to do so, remembering that Christ is King!
November 1, 2018 – Received formal permission from the City of Casa Grande to establish two monasteries on this property.
January 3, 2019 – Property purchase is complete, deed is delivered to the Brotherhood and Sisterhood.

2020



May 25, 2020 – The first day of work on the land. We begin to clear away the brush and mark the spots for the ~660 fence posts around three sides of the perimeter.
May 26, 2020 – The ~660 holes for the fence posts are dug and inspected one by one.
May 27, 2020 – We begin to cement each fence post around the perimeter.





built on the foundation of the apostles and prophets, Jesus Christ Himself being the chief cornerstone,



September 23, 2020 – The footing for the front wall is dug and we visit the property to inspect it ourselves, foot by foot.
2021




February 5, 2021 – Wall Construction Completed!
July 12, 2021 – Began Road Construction




August 12, 2021 – Road Construction Completed!
2022

2022 – A mountain of engineering docs, architectural designs, and permits to prepare the next steps of our project!
2023
February 6, 2023 – Began Water Pipes Installation